Urbanest Student Village

Project Number
A080314
 
Designer
Anthony Freeman
 
Client
Nardia Plumbing
Architect
Cox Rainer
Builder
John Holland Group
Value (Build Cost)
$ 80 Million
Hydraulics Contractor
Nardia Plumbing

Project Duration
March 2008 to December 2009
 
Innovations
Pre-fabricated bathroom pods were built off site

A heat trace system was used to maintain the heat within the hot water services in lieu of a secondary piped circulating system

Grey water from waste fixtures was treated and re-cycled for irrigation
Specific Challenges
The pre-fabricated batroom pods where manufactured in Italy and did not comply with Australian plumbing standards. Alterations where reuired to be made to each pod to achieve plumbing approval
Services Documented
  • Cold Water Service,
  • Hot Water Service,
  • Fire Hydrant Service,
  • Fire Hose Reel Service,
  • Gas Service,
  • Sanitary Drainage and Plumbing,
  • Downpipes and Gutters
  • Stormwater Drainage

Aqualogical | Hydraulic Consultants